The only thorough coverage of project management for industrial construction projects
Table of ContentsPreface
The Author
1. Introduction
2. Project management
2.1 Principal of project management
2.2 project characteristic
2.3 Project life cycle
2.3.1 Initiation of the Project
2.3.1.1Getting to the Scope Baseline
2.3.2 Feasibility Study
2.3.3 Feed (Preliminary) Engineering
2.3.4 Detail engineering
2.3.5 Decision support package
2.3.6 Design management
2.3.7 Execution phase
2.3.8 Commissioning and startup
2.4 Is this project successful?
2.4.1 Project management goals
2.5 Project management tasks
2.6 Project manager skill
3. Economic risk analysis
3.1 Introduction
3.2 project cash flow
3.2.1 The depreciation methods.
3.2.2 Method of net present value NPV
3.2.2.1Inflation rate
3.2.3 Minimum Internal rate of return (MIRR)
3.2.4 Payout Method
3.3 Economic risk assessment
3.3.1 Probability theory
3.3.2 Probability Distribution of your variables
3.3.3 Distribution for uncertainty parameters
3.3.4 Choose the appropriate probability distribution
3.4 Decision Tree
3.5 Monte-Carlo simulation technique
3.6 Risk Adjusted Value (RAV)
4. time planning
4.1 introduction
4.1.1 plan single point of accountability (SPA)
4.1.2 the way of starting the plan
4.1.3 work breakdown structure WBS
4.2 Responsibilities of the team work
4.3 Expected activity time period
4.4 Calculate the Activity time period
4.5 Time schedule preparation
4.5.1 Gantt Chart
4.5.2 Critical path method (CPM)
4.5.3 Program Evaluation and Review Technique (PERT)
4.5.4 Example:
4.5.5 Application for PERT Method
4.5.5.1Statistics calculation for activity time
4.5.5.2 Example:
4.6 Planning Overview
5. Resource management
5.1 Introduction
5.2 Project organization
5.2.1 Types of organizations
5.2.2 Select the best organization
5.3 Project manager as a leader
5.4 Administrative organization for total quality management
5.5 Team members selection
5.6 Managing the team
5.7Allocate resources to project plan
5.8Relation between project parties
5.9 Document and information transfer
5.10 Information transfer
5.11 Quality control in design phase
5.11.1 Inputs and outputs of the design phase
5.11.2 Design verification
5.11.3 Change in the design
5.11.4 approval of the design
6. Cost management
6.1 introduction
6.2 Cost types
6.2.1 Cost estimate
6.2.2Steel structure cost estimate
6.2.3Detailed cost
6.2.4Cost estimate to project control
6.3 Economic analysis to project cost
6.3.1 Work Breakdown Structure (WBS)
6.3.2 Organization breakdown Structure (OBS)
6.3.3 OBS/WBS matrix
6.3.4 Work Packages
6.3.5 Cost control
6.3.6 (S) Curve
6.4 Cash flow calculation
6.4.1 project Cash flow
6.4.2 Impact on increasing cost:
6.4.3Project late impact
6.4.4 Impact of operation efficiency
7. Bidding, tenders and Contracts
7.1 Introduction
7.2 Contracts
7.2.1 measured contract
7.2.2 Lump Sum
7.2.3 Cost Plus
7.3 Contract between the owner and engineering consultancy office
7.4 The importance of contracts in assuring the quality of the project
7.5 Contracts in ISO
7.6 FIDIC contracts
7.7 General conditions in the contracts
7.8 Arbitration and the arbitrator
7.9 Bids and tenders
7.9.1 Public (Open) tender
7.9.2 Limited Tender
7.9.3 Negotiated Tender
7.9.4 Direct order
7.9.5 Tender technical evaluation
7.9.6 Commercial evaluation
7.9.6.1 Commercial evaluation Methods
7.10 Closeout report
8- Quality from theory to reality
8.1 Introduction
8.2 Quality system
8.3 ISO 9000
8.4 Quality management requirements
8.4.1 Quality manual
8.4.2 Quality Plan:
8.4.3 Quality control
8.4.3.1 Why is Quality Control Important?
8.4.3.2 Submittal Data
8.4.3.3 How to Check Incoming Materials?
8.4.3.4 Methods of Laying Out/Checking Work
8.4.3.5 Material/Equipment Compliance Tests
8.4.3.6 When to Inspect Work
8.4.3.7 Paperwork/Documentation
8.4.3.8 Quality Control Plans
8.4.4 Quality assurance
8.4.4.1 Quality assurance in the ISO
8.4.4.2 The responsibility of the manufacturer
8.4.4.3 responsibility of the owner
8-5 project Quality Control in various stages
8.5.1 feasibility study stage
8.5.2 Feed (Preliminary) Engineering
8.5.3 Detail Study
8.5.3.1 Design quality control
8.5.4 Execution phase
8.5.4.1 ISO and control work
8.5.4.2 inspection procedures
8.5.4.3 importance of contracts in assuring the project quality
8.5.4.4 checklists
8.6 operational phase of the project
8.7 Total Building commissioning System
8.7.1 Planning Stage
8.7.1.1Identify commissioning team
8.7.1.2 Define Owner's Project Requirements with the Customer Agency
8.7.1.3 Develop Preliminary Commissioning Plan
8.7.1.4 Commissioning for Certifications (LEED, Energy Star, etc.)
8.7.1.5 Commissioning Agent Costs
8.7.2 Design Stage
8.7.2.1 Incorporate Commissioning into A/E & CM Scope of Services
8.7. 3 construction stage
8.7.3.1 Review Submittals for Performance Parameters
8.7.3.2 Develop & Utilize Construction Checklists
8.7.3.3 Oversee & Document Functional Performance Testing
8.7.3.4 Test Data Records
8.7.3.5 Hold Commissioning Team Meetings & Report Progress
8.7.3.6 Conduct Owner Training
8.7.3.7 Turnover Commissioning Record
8.7.4 Building Commissioning Process Post-Construction Stage
8.7.4.1 Post-Construction stage
8.7.4.2 Perform Deferred & Seasonal Testing
8.7.4.3 Reinspect/Review Performance before End of Warranty Period
8.7.4.4 Complete Final Commissioning Report
8.7.4.5 Recommission Facility Every 3-5 Years
8.7.4.6 Recommissioning
8.7.5 Advantages for Total Building commissioning system
9. Project Risk management
9.1 Introduction
9.1.1 The Risk management Process
9.2 Project risks
9.3 Risk assessment
9.4 Risk Identification
9.4.1 Methods of defining risk
9.4.2 Grouping the Risks
9.5 Define priorities
9.6 Risk Response Planning and Strategies
9.7 Risk Monitoring and Control
9.8 Example:
9.9 Methods of risk avoidance
10. Quiz for project management
10.1 Introduction
10.2 questions
10.3 The Right Decision
References
Back to Top